Meeting 1 – Airport Master Plan Kickoff Meeting
October 11. 2022
This meeting introduces the public, stakeholders, agencies, and other interested parties to the Master Plan process, project schedule, scope of work, airport funding, and project goals.
Meeting 2 – Completion of Inventory and Forecast
February 23, 2023
Recheduled for March 16, 2023
This meeting will present a summary of inventory findings and the analysis and determinations of the aviation forecast. An important component of this meeting will be the presentation of the critical aircraft determination.
Meeting 3 – Completion of Facility Requirements and Presentation of Development Alternatives
April 10, 2023
This meeting will focus on the FAA design standards and recommendations required to meet the safety requirements of the critical aircraft (facility dimensions, separations, runway length, and other physical requirements). This meeting will also involve a presentation of initial development alternatives to meet any identified deficiencies in FAA design standards, recommendations, and compliance issues. This meeting will allow and invite input and discussion regarding the potential alternatives.
Meeting 4 – Presentation of Draft Documents
Date TBD September 2023
A presentation of the draft documents to the City Council will be made prior to this meeting. The public meeting will present the draft Airport Master Plan and Airport Layout Plan drawings to the community, showing the selected alternative for any needed development. Following the meeting, there will be a 30-day period for public comment. At the conclusion of the public comment period, the documents will be considered substantially complete.
Meeting 5 – Presentation of Final Documents
Date TBD January 2024
This meeting will be scheduled as an agenda item at a formal Council meeting. The final documents will be presented, and then signed and accepted by the Sponsor.